17 June 2017

17 April 2017

22 February 2017

Our new building is shaping up quite nicely. The structure is currently more than 90% done, while the overall completion (that includes installation of services, fittings and landscaping) stands at 52%.

January 2017

CRPC Walk Through Video

13 November 2016

As of this weekend, our new Church wing covering three-and-a-half levels and accommodating 60,000 sq.ft. of space is nearing the 45% completion mark.

At this time of construction, we are on the verge of appointing an Interior Design company on a design and build basis.

This company, Goldreeds Associates, was also involved in the interior design of the Council of Churches Malaysia (CCM) building along Jalan Universiti as well as churches such as the Kapar Chinese Methodist Church.

Please continue to uphold this project in your prayers and for the safety of all those working at the site.

For more information, please call our Church Redevelopment Project Committee chairman Paul Lai at 012.389.3587.

16 July 2016

As of the middle of this month, our Church redevelopment project is overall 27% completed.

All the earthworks and piling have been done, and our contractor, Luxbee Enterprise Sdn Bhd, is currently at the building works stage and just putting some M&E in place.

However, we are behind schedule by about 118 days, though we hope to make up for lost time as work moves to the Upper Ground and First floors.

The Church Redevelopment Project Committee covet your continuous prayers for the commitment from our contractor and consultants to do their best and for safety at the worksite.